Interior Pier or Reshimming System
- After having raised and secured the perimeter
grade beam, enter the crawl space under the structure.
- Using hydraulic jacks, raise the interior
floor levels to their natural position.
- Place steel shims between existing interior pier
and floor system.
- If termite shields have not previously been
installed, we will install them at a reasonable
cost upon
the request of the customer.
- After
re-shimming (Step 3), add shaker sills, as
necessary, in areas of floor system that
need reinforcement.
- If there is an insufficient amount of interior
piers, add interior piers as needed to stabilize
the interior structure and floor system.
- Remove any debris resulting from the repair
process.

|
|
|
 |
|